Preparatory works have begun on the reconstruction of the water supply network in Logavina Street, on the section from Čemerlina Street to Adžemovića Street. The Municipality of Stari Grad has planned around 109,000 convertible marks in this year's budget for the reconstruction of the complete water supply network in this part of the street, and the contractor will be the company Mibral d.o.o.
This project will solve the problem of burst pipes and water spillage in Logavina Street, especially during the winter period. Over 220 meters of new water supply pipes will be installed.
Preparatory works are currently underway, installing the primary water system so that household supply is not compromised during the works.
After laying the main pipeline, around 30 new connections will also be made. Upon completion of these works, the street will be asphalted.
Komentari (0)
Prijavite se za komentiranje
PrijavaJos nema komentara. Budite prvi!
Minuta
Sve →Iz drugih kategorija

High Representative Not Elected: Germans, French and British Sabotaged Americans, New Attempt at End of June

ČOVIĆ WITHOUT MERCY: How Those Who Brought Ademović to Office Created a Political Hell for Him




Sunny Saturday, quite warm




Tragedy in Albanian resort: Two minors drown