SARAJEVO, (Patria) - Toplane Sarajevo informs users of central heating that from September 14 to 18, 2020, between 08:00 and 16:00, functional tests will be carried out on the central heating system as a technical check of the entire heating system before the upcoming 2020/2021 heating season.
Functional tests on the central heating system will be carried out according to the following schedule:
- September 14, 2020, in the Center Regional Unit,
- September 15, 2020, in the Novo Sarajevo I Regional Unit,
- September 16, 2020, in the Novo Sarajevo II Regional Unit,
- September 17, 2020, in the Alipašino polje Regional Unit,
- September 18, 2020, in the Dobrinja, Ilidža, Ilijaš, and Hadžići Regional Units.
We ask users to report any malfunctions to their manager or the duty service of KJKP «Toplane – Sarajevo» d.o.o. at tel: 033 650 979 and 033/ 650-956.
Komentari (0)
Prijavite se za komentiranje
PrijavaJos nema komentara. Budite prvi!
Minuta
Sve →Iz drugih kategorija

High Representative Not Elected: Germans, French and British Sabotaged Americans, New Attempt at End of June

ČOVIĆ WITHOUT MERCY: How Those Who Brought Ademović to Office Created a Political Hell for Him




Sunny Saturday, quite warm




Tragedy in Albanian resort: Two minors drown